Construction Change Order Process: Steps for Design Pros

A change order is a written amendment to a signed construction contract that changes the work, the price, the schedule, or all three, and it only counts once the people who hold the contract agree to it in writing. The process that protects you is simple: describe the change, price it, state the schedule effect, get signatures, and only then do the work. The part that decides whether it goes smoothly is something that happens before the project starts: how precisely the original scope was written down. Change orders are measured against that baseline, and a vague baseline turns every change into an argument.

This guide is for designers, decorators, stagers, kitchen and bath designers and design-build teams who write scopes and live with the changes. It covers the steps, what each document must contain, who signs and who pays, and what to do when the client and the contractor cannot agree.

Scopebloom
Start with a clearer project scope
ScopeBloom turns client walkthrough conversations into detailed, branded statements of work, giving change orders a more precise baseline.
Visit

TL;DR

  • A change order is a signed amendment to the contract. Under AIA's standard approach it becomes binding when the owner, contractor and architect all sign.
  • The usual sequence: written change request, priced proposal, review, change order or directive, signatures, then work and payment.
  • Never start changed work on a verbal okay. SMACNA warns that disputed unauthorized work is rarely paid.
  • Every change order should state cost and time. Enter zero days when the schedule does not move.
  • A room-by-room original scope gives each change something exact to compare against.

Table of Contents

What a change order is, in plain terms

The American Bar Association describes a change order as the industry term for an amendment to a construction contract that changes the contractor's scope of work. Most often it modifies the work required, usually raising the contract price, or adjusts the completion time, or both. A valid one requires the owner and the contractor to agree on all terms.

Two words matter in that definition. "Amendment" means the change order becomes part of the contract, not a side note. "Agree" means a client saying "sure, go ahead" at a walkthrough is not yet a change order. It becomes one when the terms are written, priced and signed.

On a larger commercial or institutional job you will meet several related documents. A proposal request asks the contractor to price a possible change. A construction change directive tells the contractor to proceed before the price is settled. The change order is the final agreed record. On a typical kitchen remodel, the same logic applies with less paper: a written description, a price, a time effect and two signatures.

Why change orders happen

There is a common belief that change orders are mostly the result of mistakes. The AIA's learning guide says otherwise, listing the primary causes as:

  • owner-requested changes in the middle of the project
  • unforeseen or differing site conditions
  • delays beyond the parties' control
  • approved substitutions
  • insurance adjustments
  • reconciliation of allowances and unit prices
  • closeout adjustments such as back charges, punch list credits and early completion bonuses

The ABA adds that plan mistakes or ambiguities, a wish for aesthetic changes and a need to cut costs can all be handled this way. For design work, the first and the last are the daily reality: the client sees the cabinets installed and wants a different finish, or opens a wall and the plan has to adapt.

Berding & Weil, a law firm that advises on reconstruction projects, makes a useful point: the number of change orders is directly tied to the time and effort put into planning and complete construction documents. You will not eliminate changes, but the planning you do early decides how many you face and how defensible each one is.

The construction change order process, step by step

The sequence below follows the flow public owners publish. Minnesota State's construction change overview is a clear example. Smaller residential projects compress the steps but keep the logic.

Seven steps from change request to payment

Step 1: Identify the change and write it down

Someone notices a need: the client asks for a different layout, the contractor finds a hidden condition, a product is discontinued. The first job is to state it in writing, with the reason, the location and what in the existing contract documents it affects.

Where it goes wrong: changes raised in conversation on site and remembered differently a week later. The fix is to capture what was said while you are standing in the room, and to attach it to the room in the original scope. Our own tool, ScopeBloom, is built around capturing walkthrough conversations and turning them into room-by-room scopes, which gives you a dated record of what was agreed before and what was asked for later.

Step 2: Request a price and time proposal

In the AIA family, owners typically use the Proposal Request form, AIA G709-2018. SMACNA explains that it identifies the change and the parties and asks for a price and time proposal. It is not an authorization to do the work. In Minnesota State's flow, the architect or engineer sends the written request to the general contractor, who answers in writing with scope, cost and schedule details.

Where it goes wrong: treating the request as a green light. A contractor who starts on a request alone is working without authorization.

Step 3: Price the change in detail

The contractor builds the proposal. Baker Tilly's guidance lists the supporting pieces: a detailed description and reason, a fully itemized cost breakdown covering labor, materials, equipment, subcontractor costs, overhead and profit, supporting drawings and specifications, and a schedule impact analysis.

Expect change work to cost more per unit than the same work in the original bid. SMACNA reports it is common to charge 10 to 15 percent more for change work, citing the lack of a competitive environment, the difficulty of fitting the change into the existing schedule, and the paperwork and delay involved. If you are the one pricing a client's change, build that reality into your estimate rather than quoting the original per-unit rate.

Where it goes wrong: lump sums with no breakdown. A number nobody can trace invites a fight. Estimates grounded in how many hours similar work took on your past projects are far easier to defend than a guess made in the driveway.

Step 4: Review and negotiate

The owner, and the architect or designer advising them, reviews the proposal. The U.S. Army Corps of Engineers' Contract Changes Playbook describes the same logic from the owner's side: the scope must be clearly understood and documented by both parties, the owner prepares its own estimate and verifies the scope, and the parties negotiate until they reach a meeting of the minds on final cost and schedule.

Federal highway guidance asks the reviewing agency to assess why the change is necessary, its impact on the original scope, who is responsible for costs or delays, and who should pay. Those four questions work on a bathroom remodel as well as a highway.

Step 5: Issue the change order, or a directive if time is short

Once terms are agreed, the change order is written. If work cannot wait, the owner can issue a construction change directive. The ABA explains that under a directive the contractor must carry out the change even without knowing the price; under AIA form contracts the architect then determines the added compensation or time, and refusing to perform a directive is a breach of contract. A directive is a fallback for urgent situations, not a routine shortcut, and the final price still needs to be settled in a change order afterward.

Step 6: Sign before the work starts

Under AIA A201 the change order is documented on form G701 and becomes binding when the owner, contractor and architect sign. Berding & Weil's advice is blunt: before a contractor begins change order work it must be authorized in writing by the owner and construction manager, verbal authorization is a cardinal sin, and the contract should say unsigned change orders are void.

Minnesota State's flow adds a payment consequence: payment cannot be made until the change order is fully executed.

Step 7: Do the work, file the paper, get paid

The executed change order modifies the original agreement and requires the owner to pay the agreed price. Keep the signed document, the proposal, the correspondence and the revised drawings together. The City of Los Angeles Bureau of Engineering's Project Delivery Manual says the final change order file should hold the drawing and specification revisions, invoices, schedule analyses, the contractor's cost proposal, the independent estimate, a record of negotiation and relevant correspondence. On a residential job you will not need a negotiation record, but the principle holds: one folder, every change, in order.

What every change order should contain

Public agencies are the best published source of checklists, and they agree closely. The table combines what SMACNA, Virginia DOT and Baker Tilly require.

ElementWhat it should sayCommon mistake
DescriptionThe added or removed work, with plan and specification references"Extra tile work" with no room or area
ReasonWhy the change is needed and who requested itLeaving out the responsible party
PriceItemized quantities, units and unit prices, and the total increase or decreaseOne lump sum with no breakdown
TimeChanges to contract dates, or zero days if noneLeaving the field blank
Response windowA definite period for the owner to accept or rejectAn open-ended offer
SignaturesAll required parties, datedStarting work before the last signature

SMACNA, citing industry guidelines, says a proposal should state the reason for the change with plan references, the effect on time and price in enough detail to evaluate, and a definite time for the owner to accept or reject. It also says any price change should be listed whether up or down, and to enter zero days if the schedule is unaffected.

Virginia DOT's 2024 guidance for its change order form requires a description of the added or eliminated work, itemized prices with quantities, units and unit prices, and the total increase or decrease. Berding & Weil adds that a proper change order is itemized to include at minimum labor, materials, transportation, permits, coordination, supervision, overhead and profit, and reduced to a definite lump sum on approval.

Who prepares, approves and pays

Preparing. Usually the contractor prices the change and the design professional drafts or reviews it. In the Minnesota State flow the architect or engineer starts the written request and the contractor answers it. On a design-build job, the same team may do both, which makes your written record of the client's request even more important.

Approving. The AIA's best practices guide says only the client and the contractor, the parties to the construction contract, may approve changes, including to the contract sum or time. Under typical contracts the contractor, client and architect all sign. The architect advises the client but does not sign the construction contract, cannot authorize changes to it, and should not make changes affecting cost or schedule without the client's prior knowledge and express written consent. If you are a designer working under a client contract, that boundary is worth knowing: advising is your role, authorizing is not.

Paying. The owner normally pays for owner-requested changes, which is why the signature matters. Who pays for changes caused by a design error or a contractor's mistake is a contract question, and it is the most common source of cost allocation disputes, according to Baker Tilly. Settle the allocation in the contract itself, and have an attorney licensed in your state review the language if the amounts are significant.

When the parties cannot agree

Start with documentation. Berding & Weil suggests a ladder: informal negotiation, then mediation with a neutral third party, then arbitration if the contract provides for it, then litigation. SMACNA's bulletin notes that under the ConsensusDocs 200 form, if the owner and contractor dispute the cost of directed work, the owner must pay the contractor 50 percent of actual incurred costs while the rest goes through dispute resolution.

The most expensive mistake is unauthorized work. SMACNA warns that a contractor who makes an unauthorized change has little chance of being paid if the owner or architect disputes it, and that an unauthorized change affecting structural integrity or design intent can make the contractor liable through deductive change orders. It also cautions that oral change agreements are not reliably enforceable, especially for residential work. State rules on residential contracts differ, so check your state's requirements for written changes before you finalize your contract template.

Baker Tilly names the top risks as unauthorized work, incomplete or vague requests, approval delays that stall the critical path, and disputes over cost allocation. Each of the four is a documentation problem more than a people problem.

When the parties cannot agree

Why the original scope decides how painful change orders are

A change order only makes sense against something. If the original agreement says "remodel primary bath" the client can say the heated floor was always included. If it lists the room, the fixtures, the tile areas, the allowances and the exclusions, the change is easy to see: this line is new, that line is removed, this many hours at this rate.

That is the practical reason to invest in the scope before signing. A good baseline scope has these traits:

  1. It is organized by room, so any change points to a place.
  2. Every line item is specific enough to price and to dispute.
  3. Allowances and exclusions are written out, since allowance reconciliation is one of the standard causes of change orders.
  4. Photos from the walkthrough show the existing conditions, which helps when a differing condition appears later.
  5. Estimates come from real past hours, so change pricing follows the same logic as the original.

Building this by hand from notes and memory after a two-hour walkthrough is slow, and details get lost between the site and the document. That is the gap ScopeBloom fills for design studios.

How ScopeBloom supports a clean baseline

ScopeBloom is web-based software that turns recorded or live client walkthroughs into room-by-room statements of work, with transcribed line items, photos, reusable studio work lists and estimates based on your past project hours. You can edit and price the scope on desktop, prepare branded client packets from the same website, and export to design tools. Its AI assistant, Blossom, learns from past projects to give you more nuanced task estimates, so the baseline you sign reflects how your studio really works.

Scopebloom

You can start on the free tier and upgrade when the studio needs more. The paid Solo plan is $99 per month per seat or $999 per year per seat, and Pro is $149 per month per seat or $1,399 per year per seat. Studio is team-priced. See the plans on the ScopeBloom site.

A worked example: a kitchen remodel

Suppose a kitchen design-build contract lists cabinets, countertops and a backsplash in the kitchen, with a stated tile allowance. Midway through, the client asks to extend the backsplash to the ceiling on one wall and switch to a pricier tile.

  1. Written request. You record the request, the room and the date.
  2. Proposal. The tile setter prices the added area and the upgraded material. The extra square footage is priced on its own line, and the upgrade is priced as the difference over the allowance.
  3. Time. Two additional days for setting and grout, so the change order says two days. Had the schedule not moved, it would say zero.
  4. Review. The client sees the exact price and the reason. Remember that change work often carries a premium, so the estimate should reflect it from the start.
  5. Signatures. Client and contractor sign, and the designer countersigns if the contract calls for it.
  6. Work and billing. The tile goes up, the change order is billed as agreed and filed with the contract.

Nothing in this example is complicated. What makes it work is that each number points to a line in the original scope and that nobody picks up a trowel before the signatures.

FAQ

Who prepares a change order in construction?

Usually the contractor prices the change, and the design professional or project manager drafts or reviews the document. In public-sector flows, the architect or engineer starts with a written request and the contractor responds with scope, cost and schedule details. The owner and contractor, as the parties to the contract, must agree to the final terms.

Who pays for a change order?

The owner typically pays when the change is owner-requested. Responsibility for changes caused by design errors, unforeseen conditions or contractor mistakes depends on the contract language, so define allocation before the project starts. Have a construction attorney in your state review contract terms for larger projects.

Can a contractor start work before the change order is signed?

They should not. The AIA process treats the change order as binding once the required parties sign, and SMACNA warns that disputed unauthorized work is rarely paid. The one exception is a construction change directive issued by the owner, which instructs the contractor to proceed while the price is still being settled.

What should a change order include?

A description of the work added or removed, the reason, an itemized price with quantities and unit prices, the effect on schedule (zero days if none), a response deadline and all required signatures. Supporting drawings, quotes and correspondence should be filed with it.

How do you negotiate a change order?

Support the proposal with itemized costs, supplier quotes and records of time and materials, because well-documented numbers are harder to argue against. Compare the change to the original scope line by line, and remember that change work commonly costs more than the same work in the original bid. If you reach a stalemate, move up the ladder to mediation before arbitration or litigation.